The big road jobs under way or planned in Mississauga: the Ninth Line widening, the Hazel McCallion Line on Hurontario Street, McLaughlin Road and Creditview Road, and the integrated road projects in design, with the dates the City gives.
Summary
The City of Mississauga is widening 6.7 km of Ninth Line, from Eglinton Avenue West to Derry Road West, from two lanes to four, with all lanes due to open in November 2027. Metrolinx's Hazel McCallion Line is still under construction on Hurontario Street, and the City plans McLaughlin Road construction from April to December 2027. Winston Churchill Boulevard, Central Parkway East and Kariya Drive projects are still in design.
Last verified
Administered by The City of Mississauga runs City road projects; Metrolinx is building the Hazel McCallion Line; Peel Region runs projects on Regional roads. Every answer below was checked against its source on November 27, 2026; the source is linked under each one.
Under way
When will the Ninth Line widening be finished?
The City's schedule is November 2027, when construction is due to be complete and all lanes open. The City scheduled construction from spring 2026 on the 6.7-kilometre stretch from Eglinton Avenue West to Derry Road West, rebuilding the road from one lane each way to two and adding curbs, sidewalks, cycle tracks, better drainage, street lighting, transit stops and traffic signals.
The work also rebuilds and extends the triple-cell culvert under Ninth Line at the Osprey Marsh stormwater pond outlet to Sixteen Mile Creek, adding a fourth cell. An environmental assessment was completed in 2021.
When will construction on Hurontario Street for the LRT end?
Metrolinx has not given a date. Its February 12, 2026 report listed the Hazel McCallion Line as under construction, with track work done at most intersections and along the guideway and stops taking shape. The 18-kilometre line runs from Port Credit GO to the Brampton Gateway Terminal.
The City is improving McLaughlin Road, a scenic route, from Bristol Road West to Britannia Road West for pedestrians, cyclists and transit users while preserving the woodlot beside it; its renderings show one lane each way with cycle tracks and a sidewalk. The schedule is detailed design to December 2026, utility relocations from July 2026 to April 2027, construction from April to December 2027 and restoration from March to August 2028.
The City recommends it. Its implementation strategy for Creditview Road from Bancroft Drive to Old Creditview Road found traffic at mid-block and at the Bancroft Drive/Sir Monty's Drive and Kenninghall Boulevard/Crescent intersections approaching or over capacity in spring 2024, and recommends moving straight to the long-term solution, including widening to four lanes from Bancroft Drive to Argentia Road. The City says this would meet 2031 and 2041 demand and save about $4.5 million in construction costs.
Which other Mississauga road projects are still being designed?
Winston Churchill Boulevard between The Collegeway and Unity Drive/Unity Gate (preliminary design 2025-2026, detailed design 2027-2028, construction not yet scheduled); Central Parkway East between Hurontario Street and Burnhamthorpe Road East (detailed design 2028, construction 2029/2030 subject to budget); and Kariya Gate and Kariya Drive from City Centre Drive to Elm Drive West (study 2025-2026). Each combines repaving with safety, cycling and lighting improvements.
Which Mississauga road projects finished recently?
The Credit Woodlands project, which redesigned the roads around Bert Fleming Park because its rotary did not meet modern safety standards, finished its major work in October 2025 and its final work in May 2026. The Rathburn Road East (Dixie Road to Etobicoke Creek) and Ponytrail Drive project, which added cycling facilities, noise walls, stormwater and transit improvements, is also complete.
Where can I see all road construction in Mississauga?
The City's construction map shows this year's City projects with contacts, and Peel Region's interactive map shows Regional road, watermain and sewer projects. Peel's own list of major road timelines currently covers roads in Brampton and Caledon.