Shed permits in Mississauga

When a shed, gazebo or other backyard structure needs a building permit in Mississauga, and the zoning limits on how big and tall it can be and where it goes.

Summary

A one-storey, free-standing storage shed under 15 square metres with no plumbing needs no building permit in Mississauga; a bigger one, or one with plumbing, does. Zoning applies either way: on a lot under 750 square metres a shed can cover at most 10 square metres and stand 3.0 metres high, 0.61 metres from the side and rear lot lines if it is in the back yard. Larger lots allow 20 square metres, 3.5 metres and a 1.2 metre setback.

Last verified

Administered by the City of Mississauga's Building Division (permits) and zoning staff (Zoning By-law 0225-2007). Every answer below was checked against its source on November 27, 2026; the source is linked under each one.


Do I need a permit?

Do I need a building permit for a shed in Mississauga?

Not for a small storage shed. The City lists a shed less than 15 square metres, one storey tall, free-standing, without plumbing and used for storage only among the projects that do not need a permit. A shed greater than 15 square metres, or of any size that contains plumbing, needs one, as does a detached garage of any size.

No permit does not mean no rules: the City says your project must meet the zoning requirements even if it does not need a building permit, and on most smaller lots zoning caps a shed well below 15 square metres.

Source: City of Mississauga, When a building permit is required

What is the biggest shed I can build in Mississauga?

Two limits apply and the smaller one wins. For a building permit, a storage shed must be under 15 square metres (about 161 square feet) to be exempt. For zoning, each accessory building can occupy at most 10 square metres (about 108 square feet) on a lot under 750 square metres, or 20 square metres (about 215 square feet) on a lot of 750 square metres or more. So on a smaller lot a 10 by 10 foot shed (about 9.3 square metres) fits, while a 10 by 12 foot shed (about 11.1 square metres) is over the zoning limit.

Building permit needed
15 m² or more, or any size with plumbing
Zoning maximum per building, lot under 750 m²
10 m² (about 108 sq ft)
Zoning maximum per building, lot 750 m² or more
20 m² (about 215 sq ft)

The square-foot figures are conversions of the City's metric limits. Building something larger than zoning allows needs a minor variance from the Committee of Adjustment.

Source: City of Mississauga, Zoning By-law 0225-2007, Part 4.1: General Provisions for Residential Zones

Do gazebos, pergolas and play structures follow the same rules?

Gazebos have their own permit threshold: one of 10 square metres or less needs no permit, and a larger one does. More generally, any building or structure other than a shed that is larger than 10 square metres, or of any size with plumbing, needs a permit. For zoning, the City treats sheds, gazebos, outdoor fireplaces and pergolas alike as accessory buildings and structures, covered by Table 4.1.2 of the zoning by-law.

Source: City of Mississauga, When a building permit is required

Are play structures and garden suites counted as sheds?

No. Children's play equipment has its own limits in Table 4.1.3.1: it can occupy no more than 5.5 square metres, stand no more than 3.0 metres above grade, and, for a detached house, semi-detached, linked house, fourplex or street townhouse, sit in the rear yard only. The by-law also says a deck, porch, balcony, detached additional residential unit (garden suite) or detached garage is not an accessory building or structure, so each follows its own rules.

Source: City of Mississauga, Zoning By-law 0225-2007, Part 4.1: General Provisions for Residential Zones


Zoning limits: where it goes and how big

Zoning By-law 0225-2007, Table 4.1.2.2, for accessory buildings and structures in the RL, RS, R12 to R14, R16, RM3 to RM6, RM8, RM9 and RA1 to RA7 zones.

What are the zoning limits for sheds in Mississauga?

They depend on lot size. On a lot under 750 square metres, each accessory building or structure can occupy up to 10 square metres, all of them together up to 30 square metres, and each can be up to 3.0 metres high. On a lot of 750 square metres or more, the limits are 20 square metres each, 60 square metres combined, 5% of the lot area in coverage and 3.5 metres high. Height is measured to the highest point of the structure.

Accessory buildings and structures, Zoning By-law Table 4.1.2.2

Accessory buildings and structures, Zoning By-law Table 4.1.2.2
RuleLot under 750 m²Lot 750 m² or more
Maximum area, each building or structure10 m²20 m²
Maximum area, all combined30 m²60 m²
Maximum lot coverage, all combinedNot applicable5% of the lot area
Maximum height3.0 m3.5 m
Setback from interior side and rear lot lines, in the rear yard0.61 m1.2 m

In an interior or exterior side yard, the side yard regulations of the property's zone apply instead.

Table source: City of Mississauga, Zoning By-law 0225-2007, Part 4.1: General Provisions for Residential Zones

Your zone's maximum lot coverage includes every accessory building and any detached garage. If the general provisions and your property's zone regulations conflict, the zone's regulations apply.

Source: City of Mississauga, Zoning By-law 0225-2007, Part 4.1: General Provisions for Residential Zones

Where on my property can a shed go?

Not in front of the house: the by-law does not allow an accessory building between the front wall of the dwelling and the front lot line. In the back yard it must be at least 0.61 metres from the side and rear lot lines on a lot under 750 square metres, or 1.2 metres on a larger lot. A shed placed in an interior side yard has to meet the interior side yard rule of your zone, and one in an exterior side yard (beside the street on a corner lot) the exterior side yard rule.

If your lot backs onto land zoned Greenlands, larger setbacks under Subsection 4.1.8 may apply; the City's zoning map shows whether you are next to a Greenlands zone. Decks and balconies are not allowed on top of, or projecting from, an accessory building.

Source: City of Mississauga, Zoning By-law 0225-2007, Part 4.1: General Provisions for Residential Zones

How do I find which zoning rules apply to my property?

Search your address or roll number in the City's property information tool to get your zone, then read the general provisions in Table 4.1.2 of the zoning by-law alongside your zone's regulations, which may add limits such as lot coverage. The City's accessory buildings page explains this order and says the zone's rules prevail where they differ.

Source: City of Mississauga, Accessory buildings and structures (zoning)


Applying and fees

How do I apply for a shed or detached garage permit?

Apply online through ePlans like any building permit. For a shed, gazebo or detached garage the City asks for the Applicable Law Form and the Schedule 1 designer information form; a metric, scaled site plan showing property lines, existing and proposed structures, setbacks, lot area, frontage and coverage, driveway details and established grade; a floor and foundation plan with structural framing; a roof plan; and elevations of each side showing heights to the ridge and eaves.

Source: City of Mississauga, Accessory structure (shed, gazebo, detached garage): drawings and documents

How much does a shed permit cost in Mississauga?

Under the 2026 fee schedule a detached garage or shed accessory to a house is charged $6.43 per square metre, but residential permits have a $244 minimum, and a $50 non-refundable administrative fee is paid when you submit (credited toward the total). At that rate a shed would have to be larger than about 38 square metres before the calculated fee passed the minimum, so a permitted shed typically costs $244. Demolishing an accessory building is a flat $244.

The fee schedule is in effect from February 1, 2026 to January 31, 2027.

Source: City of Mississauga, Abbreviated Building Division Fees, effective February 1, 2026 to January 31, 2027

Sources

Every factual claim above traces to one of these documents.

  1. City of Mississauga

    When a building permit is required

    Retrieved November 27, 2026

  2. City of Mississauga

    Accessory buildings and structures (zoning)

    Retrieved November 27, 2026

  3. City of Mississauga

    Abbreviated Building Division Fees, effective February 1, 2026 to January 31, 2027

    Published February 1, 2026 · Retrieved November 27, 2026